Port Authority of Trinidad & Tobago – Ship To Shore Crane Rails Replacement

Complete installation of crane rails on ship to shore crane

Ship to shore container crane

Ship to shore replacement crane rails
Port Authority of Trinidad & Tobago – Ship To Shore Crane Rails Replacement
Complete installation of crane rails on ship to shore crane
Ship to shore container crane
Ship to shore replacement crane rails
The following jobs were carried out:
Cylinder head
Cylinder head dismantled at the workshop and inspected.
All mechanical works carried out by D&D Engineering Services.
The following jobs were carried out:
Liner
All liner dismounted and cleaned. All honed according to MAN instruction. After honing all liner measurement taken and B1-B2 unit dimension found out of limit. Mentioned liner strongly recommended replacing. (Measurements attached) . Recommended at next overhaul all liners be replaced.
Pistons
All pistons dismounted and cleaned. Groove measurement taken and it was found that B1, B3, B5 1st groove and A2, A3, A4, A5, A6 2nd groove measurement out of limits. All pistons to be replaced at next overhaul.
All mechanical works carried out by D&D Engineering Services.
The following jobs were carried out:
The following jobs were carried out:
Bearing and crankshaft
All mechanical works carried out by D&D Engineering Services.
The following jobs were carried out:
Pistons
All pistons dismounted and cleaned. Groove measurement taken and it was found that B1, B3, B5 1st groove and A2, A3, A4, A5, A6 2nd groove measurement out of limits. All pistons to be replaced at next overhaul.
All mechanical works carried out by D&D Engineering Services.
The following jobs were carried out:
Fuel pump inspection
Fuel pumps inspected and main plunger barrels renewed. Seals and helical barrels also replaced.
Fuel Injection valves
All mechanical works carried out by D&D Engineering Services.