Cylinder Head Components Service & Installation
Overhaul Report
Vessel Name: Atlantic Provider
Engine Type: 12V 32/40
Location: Port-of-Spain, Trinidad & Tobago.
The following jobs were carried out:
- Crankshaft deflection measurements
- Bearing and crankshaft inspection
- Cylinder head components inspection
- Fuel pump inspection
- Fuel injection valve inspection
- Liner inspection
- Piston inspection
- Valve assembly inspection
- Liner casing inspection
- Connecting rod bush inspection
- Turbocharger inspection
Cylinder head
Cylinder head dismantled at the workshop and inspected.
- Valve guide measurement taken (not acceptable) – new guides installed.
- Valve rotator inspected. (All exhaust valve rotators renewed)
- Exhaust valves and inlet valves inspected. (Unacceptable)
- Inlet and exhaust valves replaced.
- Turbochargers inspected. (Unacceptable) – both Turbochargers replaced.
- Inlet and exhaust valve seats inspected (Unacceptable) – All valve seats were replaced.
- Cylinder numbers A1, A2, A4, A5, B3, B4, B5, B6 (Oversized exhaust valve seats of 2mm were fitted)
- Starting valves serviced, all seals replaced, pilot valve seals renewed and valves tested.
- Cylinder head fire rings replaced on all 12 cylinders.
- Cylinder head sealing gasket replaced.
All mechanical works carried out by D&D Engineering Services.
Piston – Pin and Liner Service & Installation
Overhaul Report
Vessel Name: Atlantic Provider
Engine Type: 12V 32/40
Location: Port-of-Spain, Trinidad & Tobago.
The following jobs were carried out:
- Crankshaft deflection measurements
- Bearing and crankshaft inspection
- Cylinder head components inspection
- Fuel pump inspection
- Fuel injection valve inspection
- Liner inspection
- Piston inspection
- Valve assembly inspection
- Liner casing inspection
- Connecting rod bush inspection
- Turbocharger inspection
Liner
All liner dismounted and cleaned. All honed according to MAN instruction. After honing all liner measurement taken and B1-B2 unit dimension found out of limit. Mentioned liner strongly recommended replacing. (Measurements attached) . Recommended at next overhaul all liners be replaced.
Pistons
All pistons dismounted and cleaned. Groove measurement taken and it was found that B1, B3, B5 1st groove and A2, A3, A4, A5, A6 2nd groove measurement out of limits. All pistons to be replaced at next overhaul.
- Piston pin measured and found OK.
- Piston skirt inspected and found OK.
- All piston pin bearings renewed.
- Piston retaining bolts renewed
All mechanical works carried out by D&D Engineering Services.
Turbocharger Service, Overhaul & Assembly
Overhaul Report
Vessel Name: Atlantic Provider
Engine Type: 12V 32/40
Location: Port-of-Spain, Trinidad & Tobago.
The following jobs were carried out:
- Crankshaft deflection measurements
- Bearing and crankshaft inspection
- Cylinder head components inspection
- Fuel pump inspection
- Fuel injection valve inspection
- Liner inspection
- Piston inspection
- Valve assembly inspection
- Liner casing inspection
- Connecting rod bush inspection
- Turbocharger inspection
Crankpin Bearing Inspection & Installation
Overhaul Report
Vessel Name: Atlantic Provider
Engine Type: 12V 32/40
Location: Port-of-Spain, Trinidad & Tobago.
The following jobs were carried out:
- Crankshaft deflection measurements
- Bearing and crankshaft inspection
- Cylinder head components inspection
- Fuel pump inspection
- Fuel injection valve inspection
- Liner inspection
- Piston inspection
- Valve assembly inspection
- Liner casing inspection
- Connecting rod bush inspection
- Turbocharger inspection
Bearing and crankshaft
- Connecting rod bearing inspected and all 12 pairs renewed.
- Crank pin inspection completed and polished.
- #3.#5.# 7 main bearing inspection carried out. Bearing condition acceptable.
- No scratches, no visual marks, clearances & tolerances between acceptable limits.
- Thrust pad inspected. Acceptable.
All mechanical works carried out by D&D Engineering Services.
Piston Crown & Skirt Assembly
Overhaul Report
Vessel Name: Atlantic Provider
Engine Type: 12V 32/40
Location: Port-of-Spain, Trinidad & Tobago.
The following jobs were carried out:
- Crankshaft deflection measurements
- Bearing and crankshaft inspection
- Cylinder head components inspection
- Fuel pump inspection
- Fuel injection valve inspection
- Liner inspection
- Piston inspection
- Valve assembly inspection
- Liner casing inspection
- Connecting rod bush inspection
- Turbocharger inspection
Pistons
All pistons dismounted and cleaned. Groove measurement taken and it was found that B1, B3, B5 1st groove and A2, A3, A4, A5, A6 2nd groove measurement out of limits. All pistons to be replaced at next overhaul.
- Piston pin measured and found OK.
- Piston skirt inspected and found OK.
- All piston pin bearings renewed.
- Piston retaining bolts renewed
All mechanical works carried out by D&D Engineering Services.
Fuel Pump & Injectors Service, Calibration & Assembly
Overhaul Report
Vessel Name: Atlantic Provider
Engine Type: 12V 32/40
Location: Port-of-Spain, Trinidad & Tobago.
The following jobs were carried out:
- Crankshaft deflection measurements
- Bearing and crankshaft inspection
- Cylinder head components inspection
- Fuel pump inspection
- Fuel injection valve inspection
- Liner inspection
- Piston inspection
- Valve assembly inspection
- Liner casing inspection
- Connecting rod bush inspection
- Turbocharger inspection
Fuel pump inspection
Fuel pumps inspected and main plunger barrels renewed. Seals and helical barrels also replaced.
Fuel Injection valves
- All fuel injection valves dismounted and cleaned.
- Fuel valve nozzles renewed.
- Injection block lapped and sealed.
- Injectors calibrated and tested to 600 bars.
All mechanical works carried out by D&D Engineering Services.